Applicant
TrustPower Limited
Case number(s)
200620065
Decision date
Type
Decision
Decision number200620065
Application number200520109/200620099
Date25 October 2006
Offeror/applicantTrustPower Limited
Ultimate applicant beneficial ownership35.18 percent - New Zealand, Infratil Limited
28.56 percent - New Zealand, Tauranga Energy Consumers Trust
23.77 percent - United States of America, Alliant Energy Corporation
12.49 percent - New Zealand, New Zealand Public
Beneficial overseas ownership 
- Asset current0 percent
- Asset proposed23.77 percent
- Share currentN/A
- Share proposedN/A
Offeree(s)/seller(s)Dunedin City Council of New Zealand
Business activitiesElectricity, Gas & Water Supply - Electricity & Gas Supply
Details of land involved30 hectares of leasehold situated at Eldorado Track, Mahinerangi being part CTs 163047 and OT13C/300 (Otago Registry).
Regions involvedOtago
Total consideration$1
Consent soughtTo acquire an interest in land which, either alone or together with any associated land of that type, is or includes non-urban land and exceeds 5 hectares in area.
Rationale

The application has been approved as it met the criteria.

The Overseas Investment Office is satisfied that the individuals with control of the Applicant collectively have business experience and acumen relevant to the overseas investment, and that the Applicant has demonstrated financial commitment towards the overseas investment. The Overseas Investment Office is further satisfied that each individual that exercises control over the Applicant is of good character and is not an individual of the kind referred to in section 7(1) of the Immigration Act 1987.

TrustPower currently owns and operates the Waipori Hydroelectric Power Scheme (Waipori) situated 60 kilometres southwest of Dunedin. Waipori comprises a network of four dams and power station on the Waipori River and produces 190 giga watt hours (GWh) of electricity per annum. Waipori uses water principally from the Deep Stream and Upper Waipori River catchments. The principal storage for Waipori is Lake Mahinerangi, an artificial lake formed by the construction of a 34 metre high concrete arch dam.

In August 2005, TrustPower received consent (refer A200520010/D200520024) to acquire 854.0580 hectares of land as part of TrustPower's proposed Deep Stream Enhancement Project to increase electricity generation. The Deep Stream Enhancement Project is likely to provide further electricity generation of approximately 23 GWh per annum. This application is to lease approximately 30 hectares from the Dunedin City Council for the purposes of constructing a reservoir for the Deep Stream Enhancement Project.

The Deep Stream Enhancement Project proposal is likely to result in the following benefits:

  1. the creation of new employment opportunities;
  2. the introduction of development capital; and
  3. increased efficiencies and generation from TrustPower's Waipori Hydro Scheme and an increased security of supply to Dunedin City Council's water supply.
ContactJacintha Tan
Minter Ellison
PO Box 3798