Decision Type
Discretionary pastoral activity
Published date
Reference
A5539274

For this decision summary:

  • LINZ received the application before 17 November 2022
  • accordingly, the decision was made under the Crown Pastoral Land Act 1998 excluding the amendments taking effect on 17 November 2022.

Lease name(s)

Decision

Granted

What the decision relates to

Soil disturbance related to irrigation infrastructure

Duration of consent

Maintenance to continue for the life of the lease

Reasons for decision

The Commissioner of Crown Lands has determined that there are benefits to farming in terms of stock and pasture management and resilience to a changing climate from allowing the lessee to disturb soil for the purposes of irrigation infrastructure. Inherent values have not been identified in the areas, and the works have been undertaken to a good standard and are re-vegetated.

Conditions of decision

Consent is granted for soil disturbance, subject to the following conditions:

  1. Consent is granted for soil disturbance associated with irrigation infrastructure including piping, pivot points and water troughs within the areas shown outlined in blue; and for an irrigation pipeline trench along the single blue line, as shown on the plans attached.

The Crown Pastoral Land Act 1998 provides that permission to undertake the activity may still be needed under other enactments.